Construction of Raised Access Floor

Environmental requirements for applicable fields:
Temperature:10.C-35.C
Humidity:45%RH-75%RH

STEP 6. If a panel rocks diagonally when placed in the system, turn it one quarter (90 ANGLE) turn and check it again. If the panel continues to rock when rotated, some debris may be between the panel bottom and the pedestal head or stringer. Also check to make sure pedestal is not tilted, stringers are properly seated and that panel edges are flush. If the panel still rocks, set it aside to be used as perimeter cut panel. The pedestals should not be adjusted unless three or four panels supported on it are rocking. At this point, make a minor elevation adjustment to the pedestal. When installing carpeted panels, the carpet grain direction must be controlled. Each panel has an arrow on the bottom indicating proper carpet grain. All panels must be installed with the grain in the same direction. Therefore, they cannot be turned to adjust for rockers. The panel can be bumped or the pedestal assemblies adjusted. It may require two or three pedestals in a row to be adjusted.
STEP 7. If heavy equipment are to put, the panels used for bearing the heavy equipment should be strengthened with dense pedestals. If rolling materials, equipment or gang boxes across installed A/F, then 1/4-inch tempered masonite or 1/2-inch plywood should be used as pathways to avoid any damage to the top surface of the access floor panels.
STEP 8. While cutting HPL, 6-8 anti-crack holes should be made at its concave opening to prevent the crack of HPL.
Inspection standard for the panel laying
1. The ground under the raised panels and the surface of the panels should be clean and dust-free.
2. Panel surface should have no scratches, no coating drop-out and no damage of the rubber edges.
3. The panels, after being finished, should be stable and firm. People walking on them should not feel shaking and no unpleasant noise between the rub of the edges can be heard.
4. The edges of the panels should be in the same level and the height between two adjacent panels should be less than 1mm, 2.5mm in an length of 6 metres and 5mm in the whole.
5. Panels should be naturally and closely jointed with a space of less than 1mm between two adjacent panels.
If the ventilation panel with the damper is placed, the damper should be able to be adjusted easily.

1  2


Relative links>>
PVC Tile technical specification Maintenance of steel access floor
Steel access floor specification
Sketch for construction of OA floor
Maintenance of OA floor

Website designed and maintained byINTER-NET Dept.of B-star Co.,Ltd.
ALL RIGHTS RESERVED.2001-2006